Project

Medical Unit of South Carolina (MUSC) Hospital

Construction Consulting, Claims and Dispute Resolution, Health Care

Highlights

Charleston, South Carolina

Location

BGKS Joint Venture

Client

$150 million

Cost

GREYHAWK provided construction consulting and delay analysis services to the tri-venture contractor (BGKS), in settlement of a claim during construction of a new hospital. Expert consulting included responding to claims of wrongful termination, schedule delay, cost impacts, and excessive costs to complete electrical work after termination of the electrical contractor. The potential exposure to BGKS resulting from the claim approached Medical Unit of South Carolina (MUSC) Hospital5 million.

GREYHAWK worked closely with BGKS and its legal team to perform detailed analysis of hundreds of submittals, RFIs, change orders, CPM schedules, and work in place on the electrical subcontract to determine the status of work at termination, approved and pending change orders, the scope of work and budget to complete, and the efficacy of the completing subcontractor. GREYHAWK’s comprehensive analysis and mediation presentation demonstrated reasonableness of the termination and were used to achieve a successful settlement prior to litigation.

Contact Us

Let’s Work Together

Partner with us today to experience firsthand our total perspective approach. Join a thriving, dynamic and growing team with experience, skill, and passion.

You are using an unsupported version of Internet Explorer. To ensure security, performance, and full functionality, please upgrade to an up-to-date browser.