Willingboro School District – Stuart Quad
Willingboro - High School science lab
Willingboro School District – Twin Hills
Willingboro School District – Garfield East Elementary School

Project Details


  • Willingboro Township Board of Education
    Willingboro, NJ
    $67 million

    GREYHAWK is serving as the construction manager during the renovation of six elementary schools, an upper elementary school and high school. The renovations consist of a new electrical service and system, new mechanical systems to include boilers, piping, equipment and controls, new windows and exterior doors, new interior doors and hardware, new fire alarm control panels, and new security cameras and new bathrooms at all eight of the educational sites. In addition, the high school complex is receiving renovations to their auditorium, locker rooms and science labs. Hazardous materials abatement is a precursor to all construction activities.

    Pre-construction services began during the design phase and include design/constructability reviews and value engineering services to maintain the project budget. Our pre-construction services helped to tailor the bid process and bid alternates to assure our client’s project will be awarded without compromise to referendum scope basis.

    GREYHAWK’s scope for this project included HVAC commissioning. Our detailed scope included:

    • Submittal review of commissioning scope equipment/systems
    • HVAC primary system commissioning (boilers, pumps, air handling units, energy recovery units)
    • HVAC terminal equipment commissioning 20% (unit ventilators, unit heaters, exhaust fans, finned-tube radiation)
    • Building automation system commissioning
    • O&M manual review
    • Training verification